ILP = overlap among instructions via pipelining or multiple-issue. The degree of ILP is limited by dependences (program property) and hazards (pipeline property). This chapter covers loop scheduling, loop unrolling, software pipelining, and superscalar/VLIW — all static (compiler) techniques.

Definition and limits

ILP = the amount of instruction overlap achievable. Two limiters:

  1. Dependences — property of the program (dataflow, anti-, output-).
  2. Hazards — property of the pipeline (structural, data, control).

You cannot exceed the ILP the program's dependences allow, but a bad pipeline/hazard-handling can waste available ILP.

Static vs dynamic scheduling

  • Dynamic (hardware) scheduling (scoreboards, issue queues, Tomasulo) needs complex structures → high power, lower clock, harder verification.
  • Static (compiler) scheduling can often compute latencies and dependences "easily" — complex software is frequently preferred to complex hardware.
  • Argument: the compiler can schedule around known latencies; but it goes haywire under runtime cache misses (which it cannot predict). Hence both are used together in modern CPUs.

Effects of multicycle instructions

Long-latency ops create: multiple register-file writes/cycle, frequent RAW hazards, WAW hazards, and imprecise exceptions (out-of-order completion). Wider issue (fetch/decode/execute multiple instructions per stage) is one answer — handle two instructions at once.

Latency assumptions (examples)

The compiler models each producer→consumer latency as a required stall count:

Producer → ConsumerStall cycles
LD → any1
FPALU → any3
FPALU → ST2
IntALU → BR1
FPMUL → any5
FPMUL → ST4

(One branch delay slot assumed.) These numbers drive every schedule below.

Loop scheduling

Focus on loops: they account for most cycles, are easy to analyze, and repeat identically. The compiler's job is to minimize stalls.

Naive schedule — Problem (x[i] = x[i] + s)

mips
Loop: L.D   F0, 0(R1)        # load
      stall
      ADD.D F4, F0, F2       # add
      stall; stall
      S.D   F4, 0(R1)        # store
      DADDUI R1, R1, #-8     # decrement ptr
      stall
      BNE R1, R2, Loop
      stall

10 cycles/iteration — dominated by stalls for the LD→ADD (1) and ADD→SD (2) and pointer/branch (1 each) latencies.

Smart schedule

Reorder so independent work fills stalls (move the pointer update and store up):

mips
Loop: L.D   F0, 0(R1)
      DADDUI R1, R1, #-8
      ADD.D F4, F0, F2
      stall
      BNE R1, R2, Loop
      S.D F4, 8(R1)          # note offset adjusted for early ptr update

6 cycles/iteration. The anti-dependence (pointer update vs store) was easily broken because an immediate was involved. Loop overhead = 2 instrs (ptr, branch); actual work = 3 instrs (LD, ADD, SD).

Problem 1 (x[i] = y[i] * s)

Latencies: LD→any 1, FPMUL→any 5, FPMUL→ST 4, IntALU→BR 1.

  • Unoptimized (12 cycles): LD s MUL s s s s SD DA DA BNE s.
  • Optimized (8 cycles): LD DA MUL DA s s BNE SD.

Loop unrolling

Replicate the loop body to expose independent instructions and hide latencies.

Scheduled + unrolled (degree 4)

mips
Loop: L.D   F0, 0(R1)
      L.D   F6, -8(R1)
      L.D   F10, -16(R1)
      L.D   F14, -24(R1)
      ADD.D F4, F0, F2
      ADD.D F8, F6, F2
      ADD.D F12, F10, F2
      ADD.D F16, F14, F2
      S.D   F4, 0(R1)
      S.D   F8, -8(R1)
      DADDUI R1, R1, #-32
      S.D   F12, 16(R1)
      BNE   R1, R2, Loop
      S.D   F16, 8(R1)
  • Total = 14 cycles for 4 iterations = 3.5 cycles/iteration (vs 10 naive, 6 smart).
  • Loop overhead = 2 instrs; work = 12 instrs.

Costs and mechanics

  • Increases code size and requires more registers (we used F0–F16).
  • To unroll an n-iteration loop by k: execute n/k big iterations + (nmodk) leftover iterations of the original loop.
  • Automating it: (1) determine cross-iteration dependences (here loads/stores to different indices don't conflict); (2) decide if unrolling helps (only if iterations are independent); (3) compute address offsets; (4) dependency analysis to schedule without new hazards; (5) eliminate name dependences via extra registers.

Problem 2 (how many unrolls to avoid stalls?)

For x[i] = y[i] * s with FPMUL→any 5, FPMUL→ST 4:

  • Degree 2: LD LD MUL MUL DA DA 1s SD BNE SD — still some stalls.
  • Degree 3: LD LD LD MUL MUL MUL DA DA SD SD BNE SD12 cyc / 3 iter = 4 cyc/iter, no stalls.

Software pipelining

Achieves unrolling's effect without code expansion: instructions from different iterations overlap in steady state.

mips
Loop: S.D   F4, 0(R2)        # store from iter i
      MUL   F4, F0, F2        # mul   from iter i+1
      L.D   F0, 0(R1)         # load  from iter i+2
      DADDUI R2, R2, #-8
      BNE   R1, R3, Loop
      DADDUI R1, R1, #-8
  • Advantages: nearly same throughput as unrolling, no code-size blowup, almost always in steady state (unrolled loops waste cycles at start/end). Can also be unrolled further to cut loop overhead.
  • Disadvantages: does not reduce loop overhead; may require more registers (different iterations' live values coexist).

Problem 4 (x[i] = y[i] * s, sw-pipelined)

mips
Loop: S.D   F4, 0(R2)
      MUL   F4, F0, F2
      L.D   F0, 0(R1)
      DADDUI R2, R2, #-8
      BNE   R1, R3, Loop
      DADDUI R1, R1, #-8      # no stalls

Store offset tricks (e.g., S.D F4, 0(R2) then DADDUI R2) are needed because the store now belongs to an earlier iteration than the load/mul. Using more register names avoids artificial dependences.

Superscalar & VLIW

Superscalar pipelines

Multiple pipelines issue in parallel; e.g., an integer pipe (LD, SD, ADDUI, BNE) and an FP pipe (ADD.D):

mips
Loop: L.D  F0, 0(R1)        |  ADD.D F4, F0, F2
      L.D  F6, -8(R1)       |  ADD.D F8, F6, F2
      L.D  F10, -16(R1)      |  ADD.D F12, F10, F2
      L.D  F14, -24(R1)      |  ADD.D F16, F14, F2
      S.D  F4, 0(R1)        |  ADD.D F20, F18, F2
      S.D  F8, -8(R1)
      DADDUI R1, R1, #-40
      S.D  F12, -16(R1)
      BNE R1, R2, Loop
      S.D  F16, 16(R1)
  • Needs unroll by degree 5 to eliminate all stalls (fewer if the DADDUI is moved up).
  • Compiler specifies instructions that can be issued as one packet; hardware dispatches to the pipes.

VLIW

The compiler specifies a fixed number of instructions per packet (one long instruction word). Wider issue needs more unrolling to fill both pipes. Less hardware (no dynamic dispatch) but relies entirely on the compiler and loses binary compatibility across widths.

Problem 3 (superscalar, x[i]=y[i]*s)

With the int/FP split, 7 unrolls eliminate stalls (or 5 if DADDUI is hoisted). The FP mul latency (5) is the bottleneck: you need enough independent loads queued to keep the FP pipe fed while earlier muls finish.

ILP summary table

TechniqueCode sizeRegistersLoop overheadSteady-state
Naive schedulesmallfewhighpoor
Smart schedulesmallfew26 cyc/iter
Loop unrollinglargemany23.5 cyc/iter
Software pipeliningsmallmanynot reduced~3.5 cyc/iter
Superscalar (deg-5)largemany2best

Key takeaways

  • ILP is limited by program dependences + pipeline hazards; schedule around known latencies.
  • Loops are the optimization target: smart scheduling (6) → unrolling (3.5) → software pipelining (3.5, no bloat) → superscalar/VLIW (best, needs width).
  • Unrolling trades code size + registers for throughput; software pipelining trades registers for throughput without bloat.
  • Next: control hazards and branch prediction (Chapter 6) — the other big ILP limiter.